Canyon de Chelly
Administrative History
NPS Logo

APPENDIX 3:
CONSTRUCTION CONTRACTS LET SINCE 1960

1. Construct 3 Residences and Bulk L.P. Gas System
Contract:No. 14-10-0333-616
Completed:May 23, 1960
Cost:$60,075.00
Contractor:Clyde V. Hutchisan

2. Parking Areas and Access Roads
Contract:No. 14-10-0333-536
Completed:July 12, 1960
Cost:$85,721.12
Contractor:Sanders Construction Co. Ltd.

3. Comfort Station
Contract:No. 14-10-0333-671
Completed:June 3, 1961
Cost:$11,684.00
Contractor:W. H. Elliott

4. Visitor Center
Contract:No. 14-10-0333-1128
Completed:August, 1964
Cost:$118,209.68
Contractor:Flough-Slavers Co.

5. South Rim Road Stage 1 (Includes 1st and Junction Overlooks), Utilities, Bridge over Canyon de Chelly, Campground Road Extension, and Concessioner Road and Parking.
Contract:No. 14-10-0333-1581
Completed:July 18, 1966
Cost:$395,727.53
Contractor:Neilson, Inc.

6. Comfort Station and Campfire Circle
Contract:No. 14-10-3-930-14
Completed:September 20, 1967
Cost:$25,299.00
Contractor:W. D. Powell

7. Construct Residence (Duplex) and Rehabilitate Residence No. 1 (Adobe)
Contract:No. 14-10-3-930-15
Completed:September 20, 1967
Cost:$43,553.50
Contractor:Stangle Construction Inc.

8. South Rim Road Stage II (5 Miles)
Contract:No. 14-10-3-930-28
Completed:May 10, 1968
Cost:$417,002.16
Contractor:Neilson, Inc.

9. South Rim Road Stage III
Contract:No. 14-10-7-971-143
Completed:March 20, 1969
Cost:$412,422.10
Contractor:Neilson, Inc.

10. BIA-NPS Joint Road Development on the North Rim of Canyon del Muerto
Contract:No. N00 C 1420 4889
Completed:
Cost:$5,344,476.05
Contractor:Wylie Brothers Contracting Co.


<<< Previous <<< Contents >>> Next >>>


cach/adhi/app3.htm
Last Updated: 08-Mar-2004