GEORGE WASHINGTON MEMORIAL PARKWAY
Patowmack Canal and Locks (Great Falls Section)
Historic Structures Report — Architectural Data Section
NPS Logo

APPENDIX B

COST ESTIMATES/ALTERNATIVES

Costs prepared by Williamsport Preservation Training Center
February 1985

1. COST ESTIMATE/REWATER CANAL

In order to rewater the entire canal it is necessary to restore all of its operating structures to a functional condition for the following reasons:

oTo maintain water in the cut
oTo insure sufficient water and/or relieve excess water
oTo regulate the flow of water
oRestore wing dam$1,200,000
oEntrance to canal

Remove silt build up$30,000

Clear and thin vegetation25,000

Excavate canal prism25,000

$80,000
oRestore first spillway

Demolition$2,500

Restoration26,000

$28,500
oUpper guard gate

Masonry repair and restoration$110,000

Reconstruct gates75,000

$185,000
oCanal to lower spillway

Excavation$12,000

Clear and thin vegetation12,500

Repair canal walls65,000

$89,500
oLower spillway

Restore to operating level of canal$45,000
oExcavate canal from lower spillway to Grist Mill$8,500
oGrist mill site

Restoration of mill outlet to retain water at operating level of canal$26,000
oCanal from mill site to holding basin excavation$128,000

Stabilization of canal walls275,000

Removal of existing walkway8,500

$411,500
oHolding basin

Clear cut vegetation within berm$14,000

Selective cutting of mature trees8,500

Excavation90,000

Restoration of berm35,000

$147,500
oReconstruct waste weir$46,000
oReconstruct lower basin feeder gate$16,000
oLower guard gate

Restoration and stabilization of masonry$75,000

Reconstruct gates65,000

$140,000
oLock 1

Excavation$7,000

Masonry stabilization and restoration150,000

Reconstruct floors, sills, gates and hardware450,000

$607,000
oLock 2

Excavation$7,500

Masonry stabilization and restoration300,000

Reconstruct floors, sills, gates and hardware450,000

$757,500
oLower holding basin

Excavation$8,000

Clear cut vegetation12,000

Reconstruction of walls40,000

$60,000
oLock 3

Excavation$7,000

Restore west (land side) wall150,000

Reconstruct east wall250,000

Reconstruct timber framing, gates and hardware220,000

$627,000
oLock 4 and 5

Clear debris$5,000

Reconstruct timber framing400,000

Reconstruct masonry150,000

Reconstruct gates450,000

Reconstruct operating hardware100,000

$1,105,000
oSelective clearing of vegetation at locks$12,000
oReconstruct visitor walkway from mill site to Locks 3, 4 and 5$38,000

TOTAL$5,630,000


2. COST ESTIMATE/DRY CANAL

oCanal Prism

Construct earthberm at upstream entrance$33,000

Backfill canal prism to operating level345,000

Install subsurface drainage165,000

Construct pedestrian walkway185,000

Clear and thin vegetation, reseeding29,000

Construct culvert at Mine Run140,000

Stabilize and restore masonry structures145,000

$1,042,000
oHolding Basin

Stabilize stone retaining wall$45,000

Selective restoration of masonry features46,000

Clear & thin vegetation, reseeding8,000

Provide earth fill to operating level9,000

Construct pedestrian walkway and bridge26,000

Paving to delineate land side of canal235,000

$369,000
oHead Gate

Selective restoration and stabilization of masonry$31,000

Earth fill to operating level26,000

Clear and thin vegetation, reseeding8,000

$65,000
oLock 1

Selective restoration and stabilization of masonry$45,000

Excavate lock to historic elevation7,000

Reconstruct two pairs of lock gates435,000

Provide subsurface drainage6,000

Backfill at lock ends15,000

Construct stair and walkway15,000

Clear and thin vegetation, reseeding35,000

$558,000
oLock 2

Selective stabilization and restoration of masonry$90,000

Install subsurface drainage20,000

Construct retaining wall15,000

Earth fill to operating level31,000

Clearing, thinning, and reseeding9,000

$165,000
oLocks 3, 4, and 5

Stabilize masonry$44,500

Clearing, thinning, and reseeding27,000

Earth fill to operating level18,500

Construct pedestrian walkway in gorge with barrier at river end26,500

Clear debris in gorge5,000

$121,500
TOTAL$2,320,500


3. COST ESTIMATE/IMPOUNDMENT

oPartial rewatering of the canal, using water from mine run to impound water from the upstream entrance to the grist mill site.
oCanal entrance

Clearing and thinning vegetation$8,000

Earthberm dam with riprap on river side and overflow structure for excess water from mine run33,000

$41,000
oFirst spillway

New riprapped earthberm over existing stone remains$9,500
oCanal to lower spillway

Clearing & thinning vegetation$12,500

Selective repairs to stone walls87,000

$99,500
oRegrade canal bed$145,000
oLower spillway$37,000
oCanal from lower spillway to grist mill

Excavation and dewatering operations, cutback and riprap at existing draining entering canal$137,000
oGrist mill site

Construction of outlet point, waste weir and spillway$26,000

Riprapped earthberm at limit of impounded area8,000

$34,000


SUBTOTAL$503,000


4. COST ESTIMATE (DRY CANAL FROM GRIST MILL SITE TO OUTLET AT DOWNSTREAM END)

oFrom lower spillway to holding basin

Construct pedestrian walkway$185,000

Clear thin vegetation, reseeding (past Grist Mill Site)12,500

Stabilize and restore masonry structures58,000

$225,000
oHolding basin

Stabilize stone retaining wall$45,000

Selective restoration of masonry features46,000

Clear and thin vegetation, reseeding8,000

Provide earth fill to operating level9,000

Construct pedestrian walkway and bridge26,000

Paving to delineate land side of canal235,000

$369,000
oHead gate

Selective restoration and stabilization of masonry$31,000

Earth fill to operating level26,000

Clear and thin vegetation, reseeding8,000

$65,000
oLock 1

Selective restoration and stabilization of masonry$45,000

Excavate lock to historic elevation7,000

Reconstruct two pairs of lock gates435,000

Provide subsurface drainage6,000

Backfill at lock ends15,000

Construct stair and walkway15,000

Clear and thin vegetation, reseeding35,000

$558,000
oLock 2

Selective stabilization and restoration of masonry$90,000

Install subsurface drainage20,000

Construct retaining wall15,000

Earth fill to operating level31,000

Clearing, thinning, and reseeding9,000

$165,000
oLocks 3, 4, and 5

Stabilize masonry$44,500

Clearing, thinning, and reseeding27,000

Earth fill to operating level18,500

Construct pedestrian walkway to gorge with barrier at river end26,500

Clear debris in gorge5,000

$121,500


SUBTOTAL$1,533,500
Total Cost For Partial Impoundment From Upstream Entrance To Grist Mill Site And For Dry Canal From Grist Mill Site To Downstream End.$2,037,000


<<< Previous <<< Contents>>> Next >>>


patowmack_canal_hsr/appb.htm
Last Updated: 17-June-2011