FORT STANWIX
History, Historic Furnishing, and Historic Structure Reports
|
|
Historic Structure Report
APPENDIX B. Class C Cost Estimates
Reconstruction of Fort Stanwix, Rome, New York
Based on Preliminary Drawings NPS No. 015/25000, 4 Sheets
March 22, 1973
Site Preparation |
Excavation Work |
Area east of the fort: 200' X 700' X 2.5' ave. depth |
13,000 cu. yds. | $1.60 | $20,800.00 |
Excavate Parade Ground to original elevation: 240' X 240' X 2.0' ave. depth |
4,266 cu. yds. | 1.60 | 6,825.00 |
Cellars in east barracks, two each, hand excavation: |
|
| 300.00 |
Area south of the fort: 160' X 50' X 1,0' ave. depth |
300 cu. yds. | 1.60 | 480.00 |
Deepen & widen ditch on south & west sides of fort: (400' X 2.0') + 400' X 17' X 10' |
2,800 cu. yds. | 1.50 | 4,275.00 |
Excavate area between east scarp and Liberty Street: 400' X 40' X 5.0' |
3,000 cu. yds. | 1.60 | 4,800.00 |
Excavate remaining ditch area: 600' X 10' X 35' |
8,000 cu. yds. | 1.60 | 12,800.00 |
Excavate stream bed east of the fort: 800' X 2.0' X 1.0' |
60 cu. yds. | 7.40 | 444.00 |
Install catch basin at outlet & connect to storm sewer: |
|
| 480.00 |
Excavate trench for pickets & backfill: |
1,020 cu. yds. | 7.40 | 7,541.00 |
Removal of eleven house foundations on site: |
|
| 5,000.00 |
Removal of existing pipe lines, disconnect & cap off: |
|
| 700.00 |
Removal of asphalt curbs & walks left on fort site: |
|
| 800.00 |
Removal of existing trees and tree stumps: |
|
| 1,700.00 |
|
|
| $66,945.00 |
Earth Fill |
Level parade ground and cellar holes on fort site: | 3,750 cu. yds. | $4.00 | $15,000.00 |
Southeast Bastion, fill and compact earth: | 178 cu. yds. | 4.00 | 712.00 |
Ramp, Ravelin to main bridge: | 25 cu. yds. | 4.00 | 75.00 |
Glacis, 1665 lin. ft. | 13,067 cu. yds. | 3.50 | 45,735.00 |
Redoubt, fill & compaction: | 330 cu. yds. | 3.50 | 1,155.00 |
Sally port, glacis of passageway: | 167 cu. yds. | 3.50 | 585.00 |
Bastions, less parapets, bombproofs and passageways: | 7,906 cu. yds. | 3.50 | 27,671.00 |
Fill above curtain walls in parapet: | 400 cu. yds. | 3.50 | 1,400.00 |
Fill in parapet of ravelin: | 71 cu. yds. | 3.50 | 250.00 |
Earth banquettes in bastions: | 123 cu. yds. | 4.00 | 492.00 |
Earth banquettes in redoubt: | 10 cu. yds. | 5.00 | 50.00 |
Fill south of ravelin: | 500 cu. yds. | 3.50 | 1,750.00 |
| 94,875.00 |
| ST | $161,820.00 |
Top Soil |
Area east of the fort: @ 0.2' deep | 1,040 cu. yds. | $6.40 | $6,656.00 |
Glacis: 1665 lin. ft. @ 0.2' deep | 808 cu. yds. | 6.40 | 5,171.00 |
Covered Way: 1275 lin. ft. @ .2' | 83 cu. yds. | 6.40 | 531.00 |
Counterscarp, scarp: | 234 cu. yds. | 6.40 | 1,498.00 |
Ditch: 1475 lin. ft. @ 0.2' deep | 220 cu. yds. | 6.40 | 1,408.00 |
Redoubt, glacis & parapet: @ .2' | 28 cu. yds. | 6.40 | 180.00 |
Sally port, glacis: | 15 cu. yds. | 6.40 | 96.00 |
Redoubt, banquette: 32 lin. ft. | 1 cu. yds. | 6.40 | 7.00 |
East scarp of fort: 560 lin. ft. X 10' | 36 cu. yds. | 6.40 | 231.00 |
Berm: 1170' X 7' X 0.2' deep | 80 cu. yds. | 6.40 | 512.00 |
Bastions, banquettes & terrepleins: | 82 cu. yds. | 6.40 | 525.00 |
| 16,815.00 |
| ST | $178,635.00 |
Sod Work |
Parapet of Glacis: 1522' X 8' | 1,353 sq. yds. | $4.00 | $5,412.00 |
Covered Way: 1275' X 10' | 1,417 sq. yds. | 4.00 | 5,668.00 |
Covered way-Ravelin: 80' X 6' | 54 sq. yds. | 4.00 | 216.00 |
Counterscarp-scarp: 2,515' X 15' | 4,192 sq. yds. | 4.00 | 16,768.00 |
Parapet of redoubt: | 28 sq. yds. | 4.00 | 112.00 |
Banquette of redoubt: | 11 sq. yds. | 4.00 | 44.00 |
East scarp of fort: 560' X 10' | 622 sq. yds. | 4.00 | 2,488.00 |
Berm: 1,550' X 6.5' | 1,070 sq. yds. | 4.00 | 4,280.00 |
Bastions, terreplein, ramps, banquettes: | 1,376 sq. yds. | 4.00 | 5,504.00 |
Parapet of ramparts: 1,535' X 12' | 2,046 sq. yds. | 4.00 | 8,184.00 |
Parapet of ravelin: 110' X 8' | 98 sq. yds. | 4.00 | 392.00 |
| 49,068.00 |
| ST | $227,703.00 |
Slope Work |
Trim scarp, counterscarp, parapets: | 5,000 lin. ft. | $1.00 | $ 5,000.00 |
| ST | $232,703.00 |
Seeding |
Glacis: | 3 acres | $800.00 | $2,400.00 |
Ditch: | .65 acres | 800.00 | 540.00 |
Glacis of redoubt & passageway: | 650 sq. yds. | 800.00 | 20.00 |
Area east of the fort: | 3.2 acres | 800.00 | 2,560.00 |
| 5,520.00 |
| ST | $238,223.00 |
Construction Work |
Concrete Work |
Excavation work: |
|
Footings, foundation walls & piers: |
|
Retaining walls within ramparts: |
|
Retaining walls, roof & floor slabs around bombproofs and passageways, ends of casemates: |
|
Floor slabs where needed in remaining buildings: |
|
Precast "pan" construction under sod & soil of ramparts: |
|
| $200,000.00 |
| ST | $438,223.00 |
Note: Estimate prepared by Rome, N.Y. firm |
Building Construction |
West Barracks: 20' X 120' | 2,400 sq. ft. | $ 60.00 | $144,000.00 |
East Barracks: 20' X 120' | 2,400 sq. ft. | 65.00 | 156,000.00 |
Headquarters: 20' X 54' | 1,080 sq. ft. | 65.00 | 64,800.00 |
Ell addition: 15' X 10' | 150 sq. ft. | 65.00 | 9,750.00 |
Guard House: 16' X 19.5' | 312 sq. ft. | 60.00 | 18,720.00 |
Ell addition: 12' X 8' | 96 sq. ft. | 65.00 | 6,240.00 |
Storehouse: 16' X 21.5' | 344 sq. ft. | 60.00 | 20,640.00 |
Ell addition: 10' X 8' X 2 ea. | 160 sq. ft. | 65.00 | 10,400.00 |
N. Casemate: 22' X 148' trapezoidal | 2,860 sq. ft. | 80.00 | 228,800.00 |
East Casemate: 22' X 145' trapezoidal | 2,904 sq. ft. | 85.00 | 246,840.00 |
South Casemate: 22' X 137' trapezoidal | 2,794 sq. ft. | 85.00 | 237,490.00 |
West Casemate: 22' X 144' trapezoidal | 2,794 sq. ft. | 85.00 | 237,490.00 |
NW Bombproof: 14.5' X 21' | 305 sq. ft. | 50.00 | 15,250.00 |
Passageway: 6' X 55' | 330 sq. ft. | 50.00 | 16,500.00 |
NE Bombproof: 16' X 16' | 256 sq. ft. | 50.00 | 12,800.00 |
Passageway: 6.5' X 25' | 163 sq. ft. | 50.00 | 8,150.00 |
SW Bombproof: 19.5' X 20' | 390 sq. ft. | 50.00 | 19,500.00 |
Passageway: 6.5' X 40' | 260 sq. ft. | 50.00 | 13,000.00 |
Bakehs. & oven: 19' X 21' + 80 | 480 sq. ft. | 80.00 | 38,400.00 |
Passageway: 6' X 30' | 180 sq. ft | 50.00 | 9,000.00 |
Necessary: 12' X 22' | 264 sq. ft. | 60.00 | 15,840.00 |
Bridge to Necessary. 7' X 58' | 406 sq. ft. | 35.00 | 14,210.00 |
Main bridge: 10,5' X 62.5' | 657 sq. ft. | 35.00 | 22,995.00 |
Drawspan: 10.5' X 12' lifts/chain | 126 sq. ft. | 150.00 | 18,900.00 |
Main Gate & Entrance: 13,5' X 18' | 243 sq. ft. | 80.00 | 19,440.00 |
Sally Port: 9.5' X 62' | 590 sq. ft. | 90.00 | 53,100.00 |
Sentry Boxes: 3.5' X 3.5' X 7 ea. | 80 sq. ft. | 80.00 | 6,800.00 |
Gun Platforms: 11,5' X 18' X 25 ea. | 5,175 sq. ft. | 10.00 | 5,175.00 |
Whipping Post w/final 9" w/staples: |
| 250.00 |
Wood Barrels, watertight: | 20 ea. | 50.00 | 1,000.00 |
Flag Pole, double mast: 14" X 40' | l ea. |
| 2,000.00 |
Wells w/wood curb: | 3 ea. |
| 1,000.00 |
Banquettes, wooden, pressure treated: |
Curtain Walls: 516' X 3' | 1,548 sq. ft. | 10.00 | 15,480.00 |
Ravelin Walls: 80' X 3' | 240 sq. ft. | 10.00 | 2,400.00 |
Flashing under: 600' X 3.5' | 2,100 sq. ft. | 1.50 | 3,150.00 |
Fraise: 6" dia. 12" o.c. 1,800 poles, pointed | 25.00 ea. |
| 45,000.00 |
Pickets, main palisade w/ribband and pointed ends, pressure treated: 1,822 poles | 30.00 ea. |
| 54,600.00 |
Pickets in redoubt w/ribband: 70 poles, pointed | 30.00 ea |
| 2,100.00 |
Outer picket gate, double: 10' X 10' |
| 1,200.00 |
Sally Port picket gate, single: 3' X 7' |
| 450.00 |
Ravelin gate, double, solid: 10' X 10' |
| 1,800.00 |
Log retaining wall at redoubt 24 lin. ft. pressure treated: |
| 500.00 |
Log retaining wall at entrance 80 lin. ft. pressure treated: |
| 1,800.00 |
Pickets for ends of earth banquettes: 1800 @ 3" X 2.5' @ 0.50cent |
| 900.00 |
Steps to sentry boxes: 4 sets |
| 355.00 |
Ravelin, Log work in walls, pressure treated: 55,030 b.m. X $800.00 M + labor costs |
| 110,060.00 |
Ravelin, platform & frame: | 450 sq. ft | 40.00 | 58,000.00 |
Ramparts, Log work, pressure treated after fitting: |
Exterior walls below embrasures: 371,960 b.m. @ $800.00 M ± labor costs |
| 595,136.00 |
Parapets, embrasures, cross ties: 204,750 b.m. @ 800.00 M ± labor costs |
| 491,400.00 |
| 3,058,871.00 |
| ST | $3,497,094.00 |
Utilities |
Telephone: 4" plastic, 720' @ $6.00 + one pullbox |
Water supply: 4" D.I.P., 400' @ $8.00 + controls |
Storm sewer: 15" R.C.P., 440' @ $14.00 ± drop inlet |
Sanitary sewer: 8" A.C.P., 400' @ $11.50 |
Primary electrical service: 3 phase, 120/208 v 400 amp. |
6" A.P.C., 465' + one pullbox @ $18.00 |
Secondary electrical service: 8" A.C.P., 280 lin. ft. + one pullbox @ $20.00 |
Electrical distribution, fixtures, outlets: |
Fire extinguishers: 10 @ $30.00 |
| Estimate by DSC | $ 57,000.00 |
Heating: electrical; provisions for future A.C. |
For future A.C., 4" gas line, DIP, 680' | DSC | 100,000.00 |
Plumbing: | DSC | 90,000.00 |
Fire Detection System in separate conduit: |
Intrusion Alarm System: | 5,000.00 |
| 252,000.00 |
|
ST |
3,749,094.00 |
Inflation factor: @ 5.5% per year for 3 years | 618,600.00 |
| ST | 4,367,694.00 |
Contingencies: @ 5.0% | 218,385.00 |
| ST | 4,386,079.00 |
Contractor's Overhead & Profit: @ 16% | 733,772.00 |
| ST | 5,319,851.00 |
Balance brought forward: | $5,319,851.00 |
N.P.S. Personnel on project: 3 yrs. @ $20,000.00 | 60,000.00 |
Transportation for NPS personnel for 3 years: | 4,500.00 |
Office expenses for NPS personnel, heat, electricity, photos: | 7,000.00 |
Architect's fee for consultation and inspection: | 8,000.00 |
| 79,500.00 |
Grand Total: | $5,399,351.00 |
Note: Working drawings, specifications writing and
contract documents included in F.Y. 1974 program and is not included in the above
estimate.
Submitted by O. W. Carroll
March 22, 1973
fost/history/hsr-appb.htm
Last Updated: 26-Dec-2008
|