MAINTENANCE COSTS
(Costs Prepared by Williamsport Preservation Training Center, February 1985)

REWATERED CANAL

YEARLY (ROUTINE) MAINTENANCE:




UNIT
COST
(1985 dollars)
MAINTENANCE COST
UPW 20 YEARS
(present value)



Cleaning Canal Bed$15,000.00$158,850.00
Selective Repairs to Canal Walls10,000.00105,900.00
Selective Repairs to Lock Walls5,000.0052,950.00
Maintaining Water Seal of Lock Gates and Guard Gates, Waste Weir12,000.00127,080.00
TOTAL
$444,780.00


CYCLIC MAINTENANCE AND/OR REPLACEMENT COSTS:

Wing Dam Repairs — 3 year cycle$35,000.00$118,650.00
Selective Timber Operations (Tree 5,000.00 Thinning) — 5 year cycle5,000.009,200.00
Gate Replacements at Locks, Guard Gates, Etc.:
    a) Lower Gates at No. 5 Lock — 20 year cycle90,000.0023,400.00
    b) Other Lock Gates — 20 year cycle80,000.0020,800.00
    c) Upper Guard Gate — 20 year cycle30,000.007,800.00
    d) Lower Guard Gate — 20 year cycle15,000.003,900.00
    e) Waste Weir at Holding Pond — 10 year cycle3,000.002,310.00
    f) Feeder Gate at Holding Pond — Pond — 20 year cycle3,000.00780.00
Locks — Timber Framing Including Flooring and Sills — 5 year cycle5,000.009,200.00
TOTAL
$196,040.00

DRY CANAL

YEARLY (ROUTINE) MAINTENANCE:




UNIT
COST
(1985 dollars)
MAINTENANCE COST
UPW 20 YEARS
(present value)



Grass Mowing$20,000.00$211,800.00
Reseeding1,000.0010,590.00
Selective Repairs to Canal Walls5,000.0052,950.00
Selective Repairs to Lock Walls5,000.0052,950.00
Selective Maintenance to Lock Gates1,000.0010,590.00
TOTAL
$338,880.00

CYCLIC MAINTENANCE AND/OR REPLACEMENT COSTS:

Selective Timber Operations (Tree Thinning) — 5 year cycle$5,000.00$9,200.00
Gate Replacements:
    a) Lower Gate at End of Walkway at No. 5 Lock — 10 year cycle2,000.001,540.00
    b) No. 1 Lock Gates — 20 year cycle40,000.0010,400.00
    c) Earthen Berm Dam at North Entrance — 10 year cycle2,000.001,540.00
TOTAL
$22,680.00

IMPOUNDMENT OF WATER IN PATOWMACK CANAL

YEARLY (ROUTINE) MAINTENANCE:




UNIT
COST
(1985 dollars)
MAINTENANCE COST
UPW 20 YEARS
(present value)



Cleaning Canal Bed$5,000.00$52,950.00
Selective Repairs to Canal Walls5,000.0052,950.00
Selective Repairs to Lock Walls5,000.0052,950.00
Selective Maintenance on Lock Gates1,000.0010,590.00
Preventive Maintenance on Waste Weir at Grist Mill Site2,000.0021,180.00
Grass Mowing and Reseeding12,000.00127,080.00
TOTAL
$317,700.00

CYCLIC MAINTENANCE AND/OR REPLACEMENT COSTS:

Selective Timber Operations (Tree Thinning) — 5 year cycle$5,000.00$9,200.00
Gate Replacements:
    a) Lower Gate at End of Walkway at Lock No. 5 — 10 year cycle2,000.001,540.00
    b) No. 1 Lock Gates — 20 year cycle4,000.001,040.00
    c) Earthen Berm Dam at North Entrance — 10 year cycle2,000.001,540.00
    d) Waste Weir at Grist Mill Site — 10 year cycle2,000.001,540.00
TOTAL
$14,860.00

PROPOSED 20-YEAR MAINTENANCE COSTS

Below are the cost estimates for the three proposed alternatives for the Potowmack Canal. For the purpose of comparison, estimates include maintenance costs for a 20-year operating cycle.



REWATERED
CANAL
DRY
CANAL
IMPOUNDMENT

Initial Cost to Implement Plan$5,630,000.00$2,320,500.00$2,037,000.00
Sub-Totals$5,630,000.00$2,320,500.00$2,037,000.00

Yearly Maintenance (For 20 years)$447,780.00$338,880.00$317,700.00
Cyclic Maintenance (For 20 years)$196,040.0022,680.0014,860.00
Sub-Totals$643,820.00$361,560.00$332,560.00


GRAND TOTALS$6,273,820.00$2,682,060.00$2,369,560.00