Golden Spike
Cultural Landscape Report
|
|
CHAPTER 2:
SITE HISTORY (continued)
Construction Methods and
Specifications
The proposed route for the new railroad passed through nearly 1,800
miles of land claimed primarily by the federal government and by various
American Indian tribes. Most of this land was still in the public
domain, and the government addressed its proposed uses in the
development of a set of specifications that were defined in Section 2 of
the Railway Act of 1862. In these specifications, Congress "granted the
right of way and the privilege of taking materials from the public lands
for the construction of the road and of the telegraph line; also in
alternate sections, on each side of the road, twelve thousand eight
hundred acres of land per mile" (The Union Pacific Railroad from Omaha
Nebraska across the Continent Its Construction, Resources,
Earnings, and Prospects 1867:1). From the sale of these lands, the
railroads could also further finance their construction and encourage
settlement of the West.
Numerous contracts were awarded to a variety of individuals as well
as to established construction companies in order to furnish the
supplies needed to keep the crews working along the line. The majority
of the supplies were hauled from the east or west coast by rail and then
transported to the staging areas and supply camps by wagon train. The
need for crews to have a continuous supply of railroad ties and poles
for the telegraph line seemed to be one of the most critical factors
because work could proceed no further once these supplies were no longer
available to the work crews.
The quality and overall durability of the construction of the
railroad was a concern of many from the outset. In response to requests
from professionals as well as from the general public, Congress
appointed a special commission to solicit input from the professional
community regarding the development of construction specifications for
the Pacific Railroad project. These specifications were presented in a
report, dated February 24, 1866 and entitled Report of Board Convened
to Determine on a Standard for Construction of the Pacific Railroad.
The report described the specifications that were required for the
various elements of construction. One of the problems with the
government's system of checks and balances regarding review, and
approval, of the 20-mile sections of railroad was that the
specifications did not have to be met prior to government approval. As
explained in the report:
. . . the board have endeavored to make such a standard as will
secure a good track without retarding the progress, and advise that
every step of the work be made with a view to ultimate perfection. Thus,
while the board deem it essential that the work shall be thoroughly
ballasted, and all the bridges provided with masonry piers and
abutments, yet, knowing that the high embankments will require some time
to settle before the track is finally adjusted, and that in many cases,
both ballast and stone for masonry must be brought by rail, they have
thought best not to make the acceptance of any section contingent on the
completion of its masonry and ballasting, but prefer that such parts of
the road be accepted in case this work shall have been commenced and is
progressing vigorously on the preceding sections [Report of Board
Convened to Determine on a Standard for Construction of the Pacific
Railroad...February 24, 1866 (Construction Report, 1866):3].
Specific aspects of construction are stipulated in this report.
Regarding embankments and excavations, it provided that:
In all parts of the main line of road or branches, embankments should
not be less than fourteen feet wide at the grade line. Excavations, if
the cuts are lengthy, should be twenty-six feet wide, and in shorter
cuts, at least twenty-four feet; thus leaving in all cases room for
continuous side ditches of ample depth and width, so as to secure that
most essential requisite, a well-drained road-bed. Rock excavations
should not be less than sixteen feet wide, and all tunnels should be
excavated for a double track. Slopes of earth embankments should be one
and a half base to one rise [Construction Report, 1866:11].
With respect to mechanical structures, the report advised that:
Culverts and abutments for bridges and drains should be of stone,
whenever a durable article can be obtained within a reasonable distance
say from five to eight miles, depending upon circumstances;
provided that temporary trestles may be adopted upon assurances, to the
satisfaction of the commissioners, that stone abutments will be
substituted immediately after the line shall be opened, so that stone
can be transported thereon. But if good stone be too remote, then
hard-burned brick or wooden trestle work may be adopted. The wood to be
of the most durable character the country will afford; and the wood or
brick to be replaced by stone when that material can be conveyed
conveniently by rail. Bridges of stone, or iron or wood, (such as the
Howe truss, or other equally good structure,) should be used at the
discretion of the company [Construction Report, 1866:11].
Regarding ballasting, it explained that:
A railroad cannot be considered complete until it is well ballasted.
If composed of gravel or broken stone it should be from 12 to 24 inches
thick, depending on the lower material. In view of the settling of new
embankments, which require time and rains before ballasting cam be
properly placed, and also in view of the number of miles required by the
law to be constructed annually, the perfect finish of the road-bed in
this respect must be progressive and the work of time. Yet it is the
opinion of the board that such work of perfecting the ballast must
proceed as usual on first-class railroads; otherwise subsequent sections
should not be accepted, because the whole work is not then being carried
forward as a great Pacific railroad, such as the law contemplates
[Construction Report, 1866:11].
The report additionally addressed specific features of
cross-ties:
Oak or other suitable timber should be used, where it can be obtained
with reasonable transportation. When such timber cannot be had for all
the ties at reasonable cost, then the best the country affords may be
adopted; but if it be cottonwood, or similar soft material, it must be
Burnettized or kyanized thoroughly so as to increase its durability. But
in all cases the joint tie should be of oak or other suitable timber,
the better to hold the spikes at these points. There should be at least
2,400 ties to the mile. They should be eight feet long, six inches
thick, and if hewn, six inches on the face [Construction Report,
1866:11-12].
Concerning sidings, the report continued:
The length of side-tracks should be at least six per cent of the line
completed, to be increased as the number of passing trains shall demand.
Side tracks should also be laid eight feet apart in the clear between
the rails [Construction Report, 1866:12].
As the track advanced so too did the telegraph lime. The Evening
Bulletin of San Francisco explained the process of building the
telegraph line in conjunction with the railroad: "Keeping pace with the
track layers was the telegraph construction party, hauling out, and
hanging, and insulating the wire, and when the train of offices and
houses stood still, connection was made with the operator's office, and
business of the road transacted" (Ketterson and Utley 1969:40-41).
A balance in the rhythm of the different work crews was essential to
maintain the pace of construction as each crew was dependent on several
others. Starting at sunrise, the camp train would send a signal to the
supply train, which often pulled as many as 30 cars loaded with
materials and supplies. The supply train would move down the track
delivering the ties, rails, spikes, bolts, telegraph poles, wire, and
other essential supplies for the laborers.
A reporter for the Alta California depicted the process of the
Central Pacific work force as construction of the rail proceeded
eastward:
The rails, ties and other material are thrown off the train as near
to the end of the track as feasible, and then the empty train is drawn
back out of the way. At this point the rails are loaded on low flat
cars, and hauled by horses to the end of the track. The ties are handled
in the same way.
Behind comes the rail gang, who take the rails from the flat cars and
lay them on the ties. While they are doing this a man on each side
distributes spikes, two to each tie; another distributes splice bars;
and a third the bolts and nuts by which the ends of the rails are
spliced together. Then comes the spikers, two on each side, to pin the
rails to the ties. Two or more men follow to adjust and bolt the splice
bars.
As fast as a flat car is unloaded it is turned on its side to allow
the loaded cars to pass it. It is then returned to the rails and sent
back for another load.
All this time wagons are distributing telegraph poles along the
grade. Cross arms are nailed onto them. Another gang working under a
foreman of telegraph construction digs the holes for the poles and a
third gang erects the poles. It is the aim of this third gang to keep
pace with the rail gang. At times lack of wagons make[s] it impossible
to keep up the supply of poles and the telegraph gangs, who pride
themselves on never letting the track get ahead of them, utilize sage
brush, barrels, ties surreptitiously taken from the track
or anything else that would keep the wire off the ground until the
supply of poles again equal[s] the demand.
Then comes a wagon bearing a reel of wire which unrolls as the wagon
goes ahead. As the wire uncoils, it is carried up on the poles and made
fast to the insulators.
Back of the track builders follows a gang with the seven or more ties
necessary to complete the foundation for each rail. These are put into
position and spiked by another gang, which also level up the track and
leave it ready for the ballasters [Alta California, Nov. 9, 1868,
quoted in Kraus 1969b:220-221].
At day's end, the camp train moved to the end of the track, workers
hungrily ate their supper, and a wire was sent to notify Sacramento of
the number of completed miles of track.
Eastern reporters traveled west to cover the progress of the Union
Pacific Railroad. One from the New York Tribune observed that
"the astonishing rapidity with which this railroad has been built has
become the subject of general wonder throughout the country. Nothing
like it has been seen before." Vouching for the quality of construction,
this reporter noted further that approximately 2,650 ties were laid to
the mile and that the steel rails were joined by fishplates (metal
plates that held abutting rails in alignment) to make a "continuous
rail." The Tribune reporter also stated that water courses were
"spanned by substantial Howe truss bridges or by culverts of timber,"
which were to be "at once replaced by solid masonry" and the road bed
was "ballasted with broken stone and disintegrated granite," which was
brought from the Black Hills. Having traveled from Cheyenne to Omaha,
the reporter clocked the train at averaging just over 34 miles per hour
and found the road to be "remarkably smooth." (Union Pacific
1868:11).
A reporter from Philadelphia captured the rhythm of the Union Pacific
track-laying teams:
Track-laying on the Union Pacific is a science, and we, pundits of
the Far East, stood upon that embankment, only about a thousand miles
this side of sunset, and backed westward before that hurrying corps of
sturdy operatives with a mingled feeling of amusement, curiosity, and
profound respect. . . . It is an Anvil Chorus that those sturdy sledges
are playing across the plains. It is in triple time, three strokes to a
spike. There are ten spikes to a rail, four hundred rails to a mile,
eighteen hundred miles to San Francisco. That's the sum, what is the
quotient? Twenty-one million times are those sledges to be swung
twenty-one million times are they to come down with their sharp
punctuation, before the great work of modern America is complete! [Union
Pacific 1868:9].
http://www.nps.gov/gosp/clr/clr2c.htm
Last Updated: 27-Jul-2003
|