Wizard Island from the Watchman Overlook.
|
|
Construction of Rim Drive
Segment 7-A (Rim Village to Diamond
Lake Junction)
With roughly $250,000 allotted for grading
just shy of 6 miles between Rim Village and the Diamond Lake Junction,
BPR advertised for bids on May 1, 1931. P.L. Crooks Construction
Company of Portland was awarded the contract and began work in June by
establishing their camp near the Devil's Backbone. Work proceeded
quickly from Rim Village, with roughly one quarter of the job completed
in only three weeks.
The contractor's workforce of ninety men
(increased to 125 by mid-July) soon began to encounter rougher terrain,
where blasting and other means were needed to move more than 50,000
cubic yards of rock per mile. Just the first four rock cuts (which
averaged 35' in depth) consumed over half of the estimated 150,000
pounds of powder as needed for the entire job. The remaining seven cuts
were not thought to be so difficult, with the exception of one running
by the Watchman Overlook that measured over 90' deep.
In early July, the NPS made note that four
steam shovels were working to widen the existing road while "every
effort" went toward retaining "as much of the natural beauty of [this]
section as possible." One of the measures taken limited the contractor
to small quantities of powder when blasting, thus throwing rock into the
roadway rather than the "right of way." This method facilitated more
effective debris removal by truck and reduced the length of fill faces,
while preserving vegetation. Crews dug trenches at the toe of fills to
hold rocks from rolling further down slope, and protected tree trunks
with planking to prevent injury from flying rocks. The contractor later
modified this practice through using worn truck tires, placing one on
top of the other around tree trunks. This practice protected the trunk
on all sides and allowed crews to move the tires from one rock cut to
another as blasting progressed.
With all of the anticipated blasting and rock
removal, the NPS tried to warn potential visitors about finding "some
inconvenience" and advised them to take the "east drive" in preference
to the west, even forecasting that the latter might be closed for two
week intervals beginning in August. Despite this gloomy prediction,
traffic flow on the west rim remained "unhampered" throughout the
season. Much of the reason lay in constructing contiguous cuts and
fills in half sections, thereby permitting the passage of vehicles. The
project even allowed inauguration of the Rim Caravan that summer, a
regularly scheduled excursion conducted by ranger naturalists that
featured half of its sixteen stops within the first 6 miles of road
beyond Rim Village.
By November 1, the job stood at approximately
75 percent complete. This was despite utilizing "as much hand labor as
possible" to help alleviate local unemployment problems. Two of the
heaviest cuts (one being around the Watchman Overlook) remained for the
1932 season, yet the four months spent on the job that summer did not
quite bring it to completion. Aside from some finish grading, most of
the remaining work related to landscape items. These, however, remained
limited in comparison to subsequent grading contracts on other segments
of Rim Drive. Old road obliteration, for example, took place only where
abandoned sections touched on the new roadway. Consequently, long
pieces of the old Rim Road remained plainly visible from high points
such as the Watchman or Hillman Peak.
This somewhat patchy approach to landscape
work also applied to the masonry items. Whereas the contractor saw the
culvert headwalls to completion, only 250 yards of retaining wall and
guardrail were built. The latter work during the grading contract came
on the Watchman grade, where the NPS had the most concern for safety.
The need for additional masonry wall along the road margins commanded
sufficient attention, such that the NPS referred to the next contract as
"Surfacing and Guardrail" when BPR advertised for bidders in the summer
of 1932.
West Rim Drive is shown
below (at left); the route of its predecessor, the old Rim
Road-- is now part of a hiking trail along the rim.
|
Although a surfacing contract was awarded
that fall, the successful bidder (Homer Johnson Company of Portland) did
not begin work until August 1933 due to a record snow year. Barely two
months elapsed before the onset of winter suspended the job, but
unusually dry conditions allowed work to resume in April 1934. It
proceeded quickly enough for final inspection of the surfacing to take
place less than six months later, mainly because the Johnson plant
produced 550 tons of crushed rock per day.
A subcontractor, Angelo Doveri of Klamath
Falls, handled construction of the guardrails. The resident landscape
architect for the season of 1934, Armin Doerner, described a slow start
during the late spring and early summer. He found that different
workmen each tried to express "his own ideas about masonry," so it
proved difficult to obtain "a uniform type of wall" at first. When
Doerner and the BPR inspector finally agreed on the style wanted, the
work improved and proceeded at a faster pace. Sargent and Doerner
agreed to the locations of the walls, starting with two relatively short
ones near Rim Village and another of some 500' in length at the
Discovery Point Overlook. By the final inspection in October, Doerner
thought the guardrails had a "very pleasing" appearance aside from some
imperfections. One was the trimming, which made it difficult to obtain
the specified amount of weathered surface. Achieving the desired
variety of color in the walls became problematic when quarrying all of
the rock from the same locality.
The surfacing contract did not include enough
funding to provide masonry guardrail to line the outer edge of each
viewpoint, nor at the road margin where 7-A had been located along a
precipice. Engineers tried to mitigate the latter problem by banking
the road toward the inside slope, as they did along parts of the
Watchman grade. The lack of guardrail, however, became even more
noticeable at the Diamond Lake Overlook near Hillman Peak, a viewpoint
whose outer edge had initially been delineated with irregularly spaced
boulders having jutted ends. Its appearance put this substation markedly
out of character with the rest of Rim Drive, so Lange prevailed on a CCC
crew who partly buried treated logs to line the outer edge of the
overlook in 1936. Each of the logs was hewn at its ends to provide
better visual transition when spaced at regular intervals, since Lange
hoped to bring weathered boulders to the site and alternate them with
the logs. This treatment represented something of a stopgap measure in
the absence of masonry guardrail, but it functioned as a better
alternative than more crude barriers.
Doerner criticized another flaw in the
surfacing phase of road construction in 7-A in 1934. He took aim at
certain daylighted cuts (ones where equipment created open areas devoid
of vegetation) that became pullouts once they had been surfaced with
crushed rock. Not only were these unintentional additions superfluous
since plenty of stopping places had been provided in the plans, but
their appearance was so unsightly that Doerner wanted the surface
material removed. He wrote that these flat areas should be allowed to
grow over with a natural ground cover, since apparently there was no way
to haul additional material to these sites and obliterate the pullout by
bank sloping. The only obliteration stipulated in the surfacing
contract for 7-A aimed at removing the quarry and crusher site from
view, along with cleaning up the camp located near Devil's Backbone.
Johnson's reluctance to do the latter may have stemmed from plans that
targeted some of the camp buildings being used for the paving phase of
road construction during the summer of 1935.
BPR awarded the contract for paving 7-A to
J.C. Compton of McMinnville, who then started giving the road a
bituminous surface treatment. This job consisted of several steps, with
the first being the spreading of aggregate (or "prime coat," as Lange
called it). The laying of a bituminous "mat" of at least 3" in depth
came next, one extending over the entire roadway and parking areas.
Lange thought the black color of the mat fit "well with the surrounding
country," and remarked how it presented a "fine appearance in relation
to existing natural features." The last step in the paving contract
started with application of a seal coat or wearing course to a width of
18' in accordance with federal highway standards of 1932. Its black
color was then altered with a fine coat of rock, which upon rolling and
brushing, yielded what Lange called a "uniform medium gray color." The
contractor completed this step on segment 7-A by October 1935, but
returned the following year to finish a related paving job (on the North
Entrance Road, route 8) and restore the site of his construction camp
located near Devil's Backbone.
Road striping did not come until 1938, but was
in accordance with earlier advice from Lange, who advised that a
"yellow, or similar colored line" could serve the purpose. He did not
favor a continuous line over the entire road, but rather use of the
stripe on curves or other areas in need of such marking to insure the
safety of motorists.
Segment 7-B (Diamond Lake Junction to
Grotto Cove)
Pre-advertising for bids on grading the
stretch of road from the Diamond Lake (North) Junction to the point half
a mile past Wineglass took place in the fall of 1932. Insufficient
funding prevented letting a contract until September of the following
year, at which time the award went to the firm of Von der Hellen and
Pierson of Medford. The contractors went to work in October 1933, but
BPR suspended the job upon the first snowfall several weeks later. In
contrast to what NPS crews accomplished prior to the contract award in
segment 7-A, the clearing and grubbing of 7-B became the contractor's
responsibility. They moved ahead on the basis of plans calling for a
roadway of 22' with a ditch 3' wide. Another contract had to be let,
this time to Dunn and Baker of Klamath Falls, in order to widen the
roadway another 2'. This change was the result of a visit to the park
by Secretary of the Interior Harold Ickes in July 1934.
Much of the work performed on the first
grading contract in 7-B took place during the long summer season of
1934. Von der Hellen and Pierson set up camp near the Wineglass at a
secluded spot where water could be pumped from the lake some 650' below
them. In contrast to grading segment 7-A, the grading contract for 7-B
required comparatively little blasting and hauling of rock. The
contractors could thus use caterpillar tractors and scrapers in handling
the pumice material. They had some assistance from the final located
line that called for five tangents of various lengths, but with several
rock cuts required as part of preventing overly heavy curvature in the
alignment. Doerner gave Von der Hellen and Pierson high marks for not
scattering stumps beyond the clearing limits (or "right of way") when
blasting stumps, despite the road being characteristically close to the
rim in many places. He also commented on the care taken with dumping
rock at the ends of deep fills so that deep trenches at the bottom of
fill slopes might catch debris from rolling any further. The
contractors then used plenty of soil to completely cover the rock at the
bottom of such fills.
Subsequent widening of the roadway began in
September 1934, but Dunn and Baker found it impossible to take the same
protective measures. In many places crews brought the rock back up
slope by hand after it damaged trees. The road widening meant that Von
der Hellen and Pierson could disregard some of the required bank sloping
and shoulder rounding. Similar to the previous grading contract for 7-A,
however, these contractors still had responsibility for other kinds of
landscape work. Doerner reported that the masonry retaining walls and
culvert headwalls in 7-B displayed good workmanship during the long
season of 1934, though completion of these items did not come until the
following summer.
Most of the old road obliteration in 7-B came
in 1935, when Von der Hellen and Pierson hired a landscape foreman under
Lange's supervision. As resident landscape architect for the NPS, Lange
saw an obliteration program to be "of immediate value to the natural
appearance of new road construction" because it went beyond planting the
ends of old road segments as was done during the grading of 7-A. With a
crew of four to ten men, the landscape foreman planted approximately 100
whitebark pine and fifty lodgepole pine over 1.2 miles of old roadbed in
1935. The difficult growing conditions meant that some 75 cubic yards
of soil covering was used in conjunction with a scheme that included
spreading duff and small branches so as to eventually produce a
"uniform" line of planting "unnoticeable to all but those accustomed to
the old road location." Lange took a number of photographs to show the
effectiveness and appearance of such efforts, as part of his plan to
obliterate 10 miles of old road. He estimated this multi-year project
needed roughly 5,000 trees as well as 2,000 loads of soil, and required
the services of two or three foremen and twenty laborers.
Grading and widening the roadway also
necessitated what Lange called "special planting" aimed at large slopes
exposed by construction. The foreman and his crew treated two sections
of 7-B in 1935, with the first located near the Wineglass road camp
where they treated a cut slope with some trees and dark soil so as to
diminish the intensity of the vivid red color seen from Cloudcap. Work
began by digging parallel trenches filled with mountain hemlock branches
to hold the "new soil" and aid establishment of trees transplanted at
the site. This procedure was also used to conceal a white line created
by grading near Steel Point that could be seen from the Crater Lake
Lodge.
Production of surfacing material for 7-B
started even before the successful bidder, A. Milne of Portland, began
opening a quarry near the Wineglass road camp in September 1935. The
contractor set up a crushing plant there, an operation that Lange
described as well screened from the road. It could produce a relatively
large amount of material at 1,500 tons per day when running at capacity
during the short working season. Once the plant at the Wineglass road
camp produced sufficient quantities for both 7-B and 7-C, virtually all
of the actual surfacing with crushed rock took place in 1936. With the
paving of those road segments not due until 1938, BPR advised the NPS
that maintenance crews should apply a light oil treatment in the interim
to prevent loss of the soft rock quarried and processed for surfacing
material at the road camp.
Milne's subcontractor for the masonry
guardrails made good progress in only two months on the job in 1935,
completing almost half of the stipulated 450 lineal yards in segment
7-B. Lange seemed pleased with the pace at which work on the guardrails
proceeded, but he commented that the first sections of wall built where
the road first touched the rim east of Llao Rock were not entirely
satisfactory. Within a short time, however, he remarked about how this
item became "exceedingly well done" and included photographs in his
annual report of some representative guardrails from this road segment.
Failure to provide such barriers, especially
where the road ran close to a precipice concerned Lange, though he did
not cast blame for the oversight. He instead called for the NPS or BPR
to provide some rule for such areas in future contracts, whether the
remedy lay in masonry wall or partially buried logs in combination with
seated boulders. Since funds for additional masonry guardrail seemed out
of the question, logs treated with creosote of varying lengths were
placed to line road margins where the danger appeared to be the most
acute. Lange preferred logs to alternate with boulders and produced a
drawing to that effect, but the BPR district engineer did not believe
that estimates in the existing advertised contract allowed for the cost
of gathering and placing boulders. Lange nevertheless wanted spaces
left between the logs in order to allow for the future introduction of
boulders as part of a subsequent contract, so the installation of these
barriers proceeded accordingly in 1936. Logs were also used to define
islands in what Lange called "traffic control areas" at road junctions.
The surfacing contract provided for treating the Diamond Lake Junction
with partially buried logs having chamfered ends and some planting once
fine grading of the site had been completed as part of the surfacing
contract.
Segments 7-C and 7-C1 (Grotto Cove to
Kerr Notch)
Available funds for letting a grading contract
from Grotto Cove and the summit of Cloudcap in September 1933, plus
short-term uncertainty over the L-line near Mount Scott, resulted in
splitting segment 7-C away from what was now called (for contracting
purposes, at least) 7-C1. The grading contract for 7-C and the spur
road to Cloudcap (4.4 miles in all) went to Dunn and Baker, who were
also awarded the contract for widening 7-B and 7-C in 1934. It made for
a smooth transition, especially since this firm had the benefit of a
long working season that year.
Clearing and grubbing were included within the
bid items for grading 7-C, just as they had been for the previous
segment. Other similarities to previous grading contracts were items
like the masonry headwalls for culverts and the limited amount of old
road obliteration. Dunn and Baker experienced more difficulty than Von
der Hellen and Pierson with rocks rolling beyond the toe of fills during
blasting operations. Some damage, for example, resulted when in an
accidental overcharge of powder sent a large quantity of rock below a
cut near Scott Bluffs. Having to repair the damage made the most
challenging part of rough grading even slower, since the stipulated
light shooting had to be followed by construction of a retaining wall.
Superintendent Canfield described these rock formations as difficult,
but ones that the contractors handled efficiently and in the same manner
as those in segment 7-A.
After completing most of the items as part of
widening 7-B and 7-C, Dunn and Baker went to work during the summer of
1935 grading one of two units in segment 7-C1. This section of 1.5
miles extended from the Cloudcap Junction (where the spur road to the
summit diverges from Rim Drive) to Sentinel Rock. Von der Hellen and
Pierson, meanwhile, started grading the other unit of 7-C1 (a section of
2.4 miles of road between Sentinel Rock and Kerr Notch) that summer
after having finished grading in 7-B.
All the rough grading in 7-C and 7-C1 meant
that the amount of landscape work accomplished during the 1935 season
was relatively small, apart from subcontractors finishing the culvert
headwalls and some planting related to old road obliteration in the
Cloudcap vicinity. Lange made a point, however, of describing two
associated problems that rose to the top of his list to correct over the
following summer. One resulted from cuts where one side of the cut was
too low in height to be properly sloped. He acknowledged that a number
of landscaped parking areas were necessary for visitors to enjoy the
scenery and make repairs to their vehicles if necessary, but any
proliferation of unintended parking areas detracted from Rim Drive being
able to harmonize with its surroundings. Lange wanted these areas
converted into slope banks where at all possible, and then showed an
example of the recommended treatment in his annual report for 1936.
An even larger problem stemmed from
daylighting prominent viewpoints in 7-C for fill material, thereby
compounding the challenge of having to obliterate old road on soils that
tested virtually sterile. Lange began making an argument for extensive
landscape treatment of what he began to call "parking overlooks" in 7-C
and 7-C1 as part of his season ending report for 1935. He pointed to
certain examples, such as the excessive daylighting at Skell Head, in
identifying five localities for special landscape treatment as part of a
future surfacing contract.
Lange made preliminary sketches of five
parking overlooks, going somewhat beyond what had become the standard
treatment for viewpoints along Rim Drive. In addition to masonry
guardrail to delineate the edge of the rim for motorists, Lange added a
bituminous walk running the full length of the wall as well as a stone
curb to separate the viewing platform from parking. Each of the five
overlooks featured an island defined by a combination of weathered
boulders and logs so as to protect a small amount of planting that
consisted of native shrubs and trees. He argued that the islands helped
to diminish the size of each of the daylighted overlooks, thereby
placing each of them into proper scale in relation to Rim Drive. The
islands also provided greater safety by separating motorists using the
road from those leaving or entering each overlook.
Interpretive marker and parapet wall at Skell Head.
|
After describing how the stations located
along Rim Drive might appear in his season-ending report for 1935, Lange
obtained topography and other engineering data from BPR for the parking
overlooks over the following summer. Whereas segments 7-A and 7-B had
so far represented missed opportunities to properly develop the stations
and substations along Rim Drive through the contracting process, Lange
wanted to show what could be achieved at viewpoints located in 7-C and
7-C1. He included photographs in his reports of progress made at four
parking overlooks in 7-C through the surfacing contract (the same one
awarded to Milne for 7-B) during 1936, with each showing how the masonry
guardrail looked in relation to logs used for demarcating the islands.
Although still in the rough grading stage of construction, Lange
anticipated similar landscape treatments at four parking overlooks in
segment 7-C1. Rejection of bids for the 7-C1 surfacing contract in the
fall of 1936 proved to be an eventual boon to the development of the
parking overlooks, since BPR subsequently doubled the amount available
for landscaping these viewpoints. The move reflected the need to
transport and place weathered boulders, as well as the use of topsoil,
peat, and fertilizers as soil amendments prior to planting some 400
trees and 600 shrubs at the parking overlooks. Lange produced site
plans for seven overlooks located between the Wineglass and Kerr Notch
that were formally approved in December 1936 and then incorporated in
the revised set of plans, specifications, and engineering estimates used
to solicit bids at the end of June 1937.
BPR awarded the surfacing contract for 7-C1 to
the Portland firm of Saxton, Looney, and Risley in July, with the job
getting underway in late August. The contractors made relatively quick
work of spreading a base course over the 4 miles of this road segment,
completing it in the fall of 1937. The landscape component was only
half finished by the end of the season, even though the two foremen who
reported to Lange directed a crew of twelve laborers. Planting required
hauling topsoil and peat from "pits" located near Park Headquarters, in
addition to using 3 tons of fertilizer obtained in Klamath Falls. Lange
described preparation of the planting beds as a base of peat, to be
followed by placing shrubs or trees, with topsoil and fertilizer put
"around but not too close to the root system." Duff was then scattered
throughout the immediate vicinity of the planting. Crews followed the
same procedure when planting at the parking overlooks during the 1938
season, although this time they were under the supervision of new
foremen. They planted a total of 625 trees, as well as 2,300 shrubs and
plants at the viewpoints over two summers.
The masons, meanwhile, added to guardrail
previously completed in 7-C by finishing another 750 lineal feet of
guardrail in 7-C1 that season. They also continued to place what Lange
described as "excellent stone curbing" at the overlooks, in addition to
the weathered boulders indicated on the site plans. Lange also assisted
the masons by providing a working drawing for steps leading to a trail
at Sentinel Point and a sketch for the stone drinking fountain installed
at Kerr Notch. The additional touch of paving walks at four parking
overlooks in 7-C came as part of the paving contract awarded in June
1938 to Warren Northwest, a construction company with regional offices
in Portland.
The contractor erected its plant at the
Wineglass road camp over the following month, situating it so as to be
equidistant from both ends of a job that called for paving approximately
12 miles of Rim Drive between the Diamond Lake Junction to the road
summit atop Cloudcap. In contrast to the work completed in 1936 along
the 6 miles of 7-A, this contract included paving "gutters" in
accordance with guidance developed by Thomas E. Carpenter, deputy chief
architect for the NPS. His work reflected a trend toward shallower
ditches requiring less maintenance, given that the bituminous paving
acted as a seal against run off that might otherwise disintegrate
surfacing material used to protect a road's subgrade. The gutters were
to work in concert with catch basins or inlets connected to culverts
placed underneath the road at regular intervals. For this contract the
"invert" was set at 5" below the seal coat, with an actual level depth
of 3" in the paved gutter. Lange commented that the gutters had an
"excellent appearance" in his report for September 1938, but the
contractor returned in 1939 to do additional sealing because cold
weather the previous fall caused some cracking.
With the paving contract essentially
completed, Lange used a number of photos in his season-ending report for
1938 to show how landscape treatments improved typical road sections in
7-B and 7-C. In contrast to the numerous landscape items left
unfinished in 7-A, both of the latter segments exhibited good examples
of old road obliteration, bank sloping, and special landscape treatments
such as adding dark soil to reduce scars. Paving and placement of catch
basins in conjunction with the placement of backfill for gutters seemed
to signify that the new Rim Drive was "rapidly becoming a reality," with
all work projected to be finished in the fall of 1940. Lange made a
point of depicting the finished parking overlooks in 7-C and 7-C1 since
they demonstrated how to rehabilitate damaged areas while properly
developing the observation stations and substations. The only thing
missing from 7-C1 was the paving, but it went to the top of
Superintendent Leavitt's funding requests for roads and trails beginning
in 1939.
Segment 7-D (Kerr Notch to Sun
Notch)
Formal adoption of the so-called "combination
line" in December 1935 pushed BPR to finalize plans to locate Rim Drive
between Kerr Notch and Sun Notch. Instead of "skirting" Dutton Ridge as
the official press release had claimed, the road location required major
cuts on both sides. The large amount of excavation anticipated caused
BPR to split 7-D into two grading contracts, with 7-D1 originally
projected to encompass about 2.7 miles from Kerr Notch to a point on the
south side of Dutton Ridge where the road would crest. The lowest bid
on this first contract, one that required a staggering 176,000 cubic
yards of excavation, was rejected in July 1936 since it was considerably
above the engineer's estimate. The need to make an award within
existing allotments led to another advertisement for bids a month later,
this time with the distance of 7-D1 reduced to just over 2 miles. The
contract went to Orino Construction of Spokane, who then set up camp on
Sand Creek in Kerr Valley and began its clearing operations. Dunn and
Baker, meanwhile, won the contract for grading the next 2.9 miles of
road. This included both 7-D2 (which ran from the end of Orino's
contract on Dutton Ridge over to Sun Notch) and the adjoining 7-E1. They
could do little more than establish camp on Vidae Creek before the
construction season came to an end.
With the grading contract for 7-D1 estimated
to be some 70 percent excavation, Lange warned that the job required
extremely careful measures to protect trees. He made special reference
to fill material, which could escape in areas dominated by long and
continuous slopes. With blasting operations imminent in July 1937, Lange
described how the ground cover of willows and other plants located
beyond the grading line were already being struck by falling material.
It upset him enough to write that the location for 7-D should never have
been approved because of the resulting damage, though this sentence was
subsequently scratched out on his report.
Blasting by Orino over the next few weeks
gave Lange and resident engineer Struble almost opposite impressions.
Whereas Struble described the contractor's progress as unsatisfactory
due to extreme care taken with type "B" excavation, Lange wrote about
Orino permitting a number of excessive shots not in accordance with
instructions from BPR. Slides traveled, he observed, far below the
necessary line of repose. This damaged trees to such an extent that the
majority had to be removed. Crews pruned trees where blasted material
hit their tops, while cuts were treated with creosote if the damage did
not require removal. Lange gradually prevailed upon Struble to require
Orino to protect trees in subsequent blasting by shooting with less
powder. The difficulty of grading in such terrain, however, made
complete protection "almost impossible," even when trees from the
roadway were placed against those situated below the grading
line.
Cuts represented another aspect of rough
grading that detracted from what Lange had described as an area that was
"originally admired for its stately and primitive character." One of
these measured approximately 145' to the roadbed from the crest of the
cut, causing falling rocks to be a constant danger due to so much loose
material on Dutton Cliff. An "epidemic" of minor accidents kept the
park physician busy, such that Leavitt noted that the men hired by Orino
seemed especially prone to broken ribs. Not only were equipment
operators vulnerable, but also those men working on several hundred feet
of hand placed retaining wall. Lange described the wall as necessary in
order to give the roadway its designed width of 24'. He especially
liked how it blended with the surroundings from the point above Kerr
Notch, writing that the massive rocks obtained in the cuts were well
selected for color and uneven faces.
The difficulties encountered by Orino in
grading 7-D1 during the 1937 season (his crews consumed more than 60
percent of the allotted time, yet completed only a third of the job)
contrasted markedly with how Dunn and Baker fared in 7-D2. The south
and west sides of Dutton Ridge and the area above Sun Meadow required
about 50 percent rock work, but the contractors found it easier than
what engineers had estimated. Progress on grading 7-D2 stood at almost
full completion by October 1937, with only finish grading and some
landscape details expected for the following season. Lange identified
"very little" damage to trees, either in burning those cleared from the
roadway or during grading operations. He described how log cribbing
used on this job reduced injury to standing trees and noted that the
contractors retrieved all of the rocks passing beyond the desired point
of repose at the toe of each fill.
Lange seemed particularly pleased with the
masonry features along 7-D2, making special reference to what later
became known as "spillways," in his season-ending report for 1937. He
included a photograph showing a floor laid to catch run off derived from
continual seepage on slopes, to be connected with culverts as part of
cross drainage. The masonry component of this grading contract was
otherwise limited to building culvert headwalls, most of which appeared
along the south side of Dutton Ridge, where snowmelt created seasonal
drainage.
East Rim Drive along Dutton
Cliff with the Pinnacles Road below it.
|
Guardrails were to be part of the surfacing
contract, but Lange could not help noticing how the road location he so
heavily criticized opened some fine views along this section of Rim
Drive. After securing topographic data from BPR, he prepared sketches
for parking areas like Sun Notch along 7-D2. The parking areas became
part of finish grading in 1938, as did additional bank sloping and
covering a portion of the scar on Sun Grade with dark soil.
Orino completed most of the rough grading in
7-D1 during the 1938 season, but all of the time allotted for the
contract had long since elapsed. A somewhat sympathetic Lange explained
that the number and size of the retaining walls needed along the eastern
side of Dutton Ridge justified a contract extension. The hand placed
walls begun in 1937, for example, were placed on each end of a masonry
wall to span one of the fills. Others required masonry walls roughly
25' in height, with one noteworthy example exceeding twice that
measurement.
The fills settled sufficiently for
construction of masonry guardrail to move forward as part of the grading
contract for 7-D1 during the 1939 season. Lange expressed some
hesitancy in allowing Orino to extract rock from the Watchman for some
3,000 lineal feet of guardrail, but he and Leavitt relented once the
contractor agreed to use a heavy crane for obtaining material. This
method eliminated new "tote" roads and other construction impacts
associated with reopening a quarry that had been "restored" since 1936.
Struble thought the guardrail component was especially well organized
during the summer of 1939, especially since the masons had completed the
job by August 20. Lange saw the rock selection and workmanship as very
good, commenting on how the guardrail had been introduced to "best
advantage, resulting in varying curves to fit the terrain."
In his season-ending report for 1939, Lange
called the provisions for protecting the landscape in 7-D1 "commendable"
despite his misgivings about the road's location. Damaged trees were
removed, pruned, or had cuts created by flying rock treated with
creosote. Other measures included special planting on slopes below the
fills so as to reduce future damage from rock fall on the East Entrance
Road, as well as some fairly extensive bank sloping and regrading as
part of old road obliteration around Kerr Notch. Several small items
had to be deferred to future contracts, with one example being Lange's
proposal to plant the areas adjoining each of the three spillways in
7-D1 so as to better "reproduce" the natural stream bed adjoining the
road.
After inviting bids for surfacing 7-D along
with segment 7-E in August 1939, BPR awarded the contract to Orino
several weeks later. Although largely devoid of landscape items, this
job included a provision for building more than 300 cubic yards of
masonry guardrail in 7-D2. The contract centered on producing aggregate
for the next two phases of construction, so Orino set up a rock crushing
plant in June 1940 not far from the camp he occupied along Sand Creek
during the grading contract.
The nearby quarry yielded enough rock for a
base and top course of surfacing material and some 27,000 tons of
aggregate to be stockpiled for future paving of the remaining segments
of Rim Drive. This "leg up" approach to paving left a mere $70,000
needed for plant mix, labor, and equipment to place a bituminous surface
on segments 7-C1, 7-D, and 7-E. The paving job represented the final
piece after the government had spent a little more than $2 million in
contracts for building Rim Drive since 1931. Difficulties with
obtaining equipment for the rock crusher, however, hindered progress on
the surfacing contract so that production of aggregate was not completed
until September 1941. In the mean time, the contractor applied a
"double prime bituminous surface treatment" to the unsealed roadbed as a
temporary measure for carrying traffic until such time that actual
paving took place.
American involvement in World War II allowed
for only enough funding to remove slides that resulted during the winter
of 1941-42. With paving put on indefinite hold, the suggested treatment
of the parking areas became a forgotten item. Lange used a photo to
depict one such stopping place in 7-D1 as part of his final report at
Crater Lake for 1939. With the masonry guardrail completed, he remarked
that the parking areas should be given a lighter color finish than that
of the road.
Segment 7-E (Sun Notch to Park
Headquarters)
The initial P-line run by BPR assigned
segment 7-E to a route linking Sun Notch with Rim Village, but the
subsequent adoption of a "combination line" led to dividing the segment
into two pieces for contracting purposes. A sort of "middle line"
connected Sun Notch with Vidae Falls and became 7-E1, while 7-E2 roughly
corresponded to the old "low line" running from Vidae Falls to Park
Headquarters. Some adjustment to the road mileage stipulated in the
respective grading contracts was still necessary, however, due to the
uncertainty that existed in 1936 over what the site development around
Vidae Falls might entail. This resulted in shortening the contract for
grading 7-E1 by four tenths of a mile so that it could be combined with
7-D2 and then advertised for bid.
Dunn and Baker completed all of the rough
grading and most of the finish portion of the contract in 7-E1 during
the 1937 season. Just over a mile in length, 7-E1 turned out to be
relatively easy work. In running above the western margin of Sun Meadow
and along the bottom of a slide on the flank of Applegate Peak, the new
road provided Lange with an opportunity to show a particularly good
example of bank sloping through a heavy rock slide. The only other
landscape item that he or the superintendent noted in 7-E1 concerned the
need to obliterate an old "motor trail" improved by the CCC in 1933, one
that started toward Sun Notch where the old Rim Road crossed Sun
Creek.
BPR awarded the contract for grading 7-E2 to
E.L. Gates of Portland in October 1937. This meant that work on the
final 3.3 miles of Rim Drive began the following spring, with the
nagging question of whether to construct a bridge or use fill to span
Vidae Creek finally resolved. Gates constructed the fill over the
following summer, which included placement of a pipe culvert with stone
headwall at both ends. Lange estimated the contractor to have completed
90 percent of the rough grading in 7-E2 that season. Photographs in his
final report for 1938 showed ditch and slope treatment along one stretch
of road, some old road obliteration through bank sloping, and placement
of what he called a "culvert drain" with rough stone pavement less than
a mile from Park Headquarters.
Aside from planting, most of the remaining
items in the grading contract pertained to completing the road
connection below Vidae Falls to the proposed Sun Creek Campground. A
need to relieve pressure on the campground at Rim Village drove
selection of new sites, such as Sun Creek, away from where the lake
could be seen. As one of several satellite areas, NPS officials hoped
that a new campground below Vidae Falls might provide an attractive
alternative to the problems associated with overuse in Rim Village.
Superintendent Leavitt liked the Sun Creek site, but did not want it
opened for use by visitors until properly developed so as to avoid
damage to the trees and ground cover. The first step toward building
the campground came in the form of a serpentine road going down a
quarter mile from Vidae Falls to an area that once served as an informal
picnic site on the old Rim Road. A bank slope constructed at its
intersection with the Rim Drive served the dual purpose of reducing the
campground road's presence to motorists traveling the main route, yet
also afforded sufficient visibility from one road to the other.
Plans for a stopping point beneath the
waterfall called for widening the road fill on the upstream (or
northern) side of Rim Drive, so as to allow for parallel parking.
Installation of a stone drinking fountain at this parking area came in
July 1939, but construction of additional landscape features had to wait
until the subsequent surfacing contract was let. These included
building a raised walk 4' wide in front of Vidae Falls, which was
separated from the roadway by a stone curb. Just as they had in 7-D,
Lange and other NPS landscape architects anticipated distinguishing the
Vidae Falls parking area from Rim Drive through the use of pavement
having a rougher texture and somewhat lighter color finish.
Culvert headwall and
masonry guardrail (in background) along East Rim Drive.
|
Introduction of the fill spanning Vidae Creek
constituted what Lange termed as the "major landscape problem" in 7-E2.
He reported that it required more than 1,000 yards of topsoil in
preparation for planting the entire slope as part of making the fill
conform to surrounding terrain. This effort required more than 5,000
plants, shrubs, and trees. Al Lathrop, formerly one of Lange's
assistants for CCC work, had charge of a crew numbering ten men and paid
by the contractor. They needed sixteen days to plant a mix of species
that included willows, mountain hemlock, huckleberry, purple-flower
honeysuckle (twinberry), and spirea. A sprinkling system was needed so
that the plantings on the fill could initially be watered every day,
then two or three times per week until early autumn. Lange described
the source of water as a "reservoir" built at the "head" of Vidae Falls,
located about 100' above the fill and out of sight from Rim Drive. From
there a 3" line was placed to one side of the falls and connected to
smaller lines spaced about 30' on centers across the planted slopes of
the fill. He estimated it might take two or three seasons for the
planting beds to provide the desired effect.
Leavitt expressed some satisfaction in
writing to Cammerer that all grading contracts let in conjunction with
building Rim Drive were finally complete as of September 1939. Lange
mentioned this milestone in his season-ending report for the year and
optimistically projected the surfacing phase to be finished in 1940,
with the paving to follow in 1941. The surfacing of 7-E did indeed come
about over the following season, but the funding request for paving this
road segment languished throughout World War II and for more than a
decade afterward. The NPS simply had to make do using oil and asphalt
treatments aimed at protecting the subgrade and surfacing material of
this road segment.
|