Jefferson National Expansion Memorial
Administrative History
|
|
Administrative History Bob Moore |
CHAPTER ONE:
The Gateway Arch Parking Garage
One element of the Memorial's development which
remained uncompleted at the outset of the 1980s was the construction of
a parking garage, to be used by both tourists and the downtown business
community. As early as 1958, the creator of the Arch, Eero Saarinen,
conducted a feasibility study for a parking facility as part of his plan
for the overall development of the Memorial site. Despite favorable
conclusions, a lack of funds prevented any work. [1]
The City of St. Louis and the National Park Service
signed a cooperative agreement in March 1956 to construct an open-air
parking lot on the north end of the Memorial grounds. The agreement
provided for a section of land to be set aside in the northwest corner
of the Gateway Arch grounds for the garage, which would be large enough
for 1,020 vehicles. The completed facility was to be considered the
joint contribution of the United States of America and the City of St.
Louis to the completed memorial. [2]
Despite delays of more than twenty years, the desire for a parking
garage, especially on the part of the city, remained strong. In 1978,
another feasibility study was approved by the Park Service, but funding
continued to be a problem. [3] It was with
the arrival of Superintendent Jerry Schober in 1979 that the project was
put into motion again. Schober recalled:
I began to see agreements that were made by [former
JEFF superintendent] George Hartzog. Now these agreements in the past
had just sat there and let dust pile up on them. There was one made in
1956 between the City of St. Louis and the Park Service which was
finally modified in '62. [4] We had a
dinky little hole in the ground on the north end of the park which was
supposed to hold up to 320 cars and they were going to have the city
operate it. Totally inadequate. Particularly when you realize that the
whole length and breadth of this area that the Arch is on now was a big
parking lot for the city. And when we began to develop the memorial we
took that many spaces from them with the promise that we were going to
bring them more and more visitors. So as the visitation jumped up to
around 2.5 - 2.7 [million] we were taking up all the parking everywhere,
[especially] from those people who had to work downtown.
We made another agreement which enabled the Bi-State
Development Agency to design . . . and construct the tram system that
went to the top of the Arch. Bi-State became our partners. The
agreement which allowed the design and construction of the trams had a
clause that it would last until 1992 or until the bonds were paid off.
Interestingly, the bonds were paid off in 1982. Many people thought in
reading the agreement that this terminated our partnership. However,
there was a clause in the agreement which stated whichever occurrence
came last, either the 30 years (1992) or the paying off of the bonds
(1982). [5]
In 1980, the city informed the National Park Service
that it intended to build a parking garage on the site of the existing
lot, at a cost of approximately $12 million. The money was to be raised
by selling revenue bonds, but the plan fell through because the bonds
were tax exempt and so carried no federal guarantee. [6] Superintendent Schober remembered the
initial phase of the development of the parking garage project:
The agreement between the city of St. Louis and the
National Park Service . . . said that we would allow the city to come in
and develop a facility for parking cars which would take care of their
needs and ours. But it would be built at their expense. The city
certainly didn't have any money, they felt, to come in and develop [a
garage] for the National Park Service. But when I got here I worked
with the mayor who was in office at that time, Jim Conway, who . . .
consented to consider building a facility at the north end of the park.
I mentioned to him that I would give them a permit which allowed them to
construct the facility, and as soon as it was completed it would become
the Park Service's, or as soon as it was paid off.
Well, Mr. Conway, election time, was defeated, and
Mayor Vince Schoemehl was elected. So I went over and I talked with him
about the possibility of carrying out the approach that Mayor Conway and
I had agreed upon. He went along with it too. This started something
that was much too long in negotiations. We would meet about every month
and we would talk about how we were going to raise the money. The City
of St. Louis' bonding rating was very poor, about double B or something
like that. . .
At every one of these meetings I brought with me an
agent of Bi-State, who we felt should be the ones to go ahead and build
[the garage], but our agreement said that the City would build it. I
think we probably met over a period [of] about eighteen months. . . .
What I was trying to get across to the city was we wouldn't tell them
where they could find the money that they were to build with. We were
not even going to ask them where they got it. We just wanted them to
carry out their commitment. And so in trying to get this point across,
one day I said to the city officials: "My old grandpappy said: If you're
going to do your own barking you don't need a dog." . . . This is a
strange thing, but that little homespun philosophy for some reason
cleared the air.
I said: "Let me get my point across. You say, you
don't have the money to construct. I am not asking you where you get
the money. I've been bringing a gentleman to these meetings every time
we've met [the Director of Development for Bi-State, John Booth], and
Bi-State is willing to float the bonds and give you the money,
and you can build the garage thereby fulfilling our agreement." And
they said: "Oh, okay! We'll change the Park Service's [agreement]." And
I said, "No, you leave our agreement alone. The City makes an agreement
with Bi-State. You fund it, we build it, and we become then a
three way partnership." Well, you'd be shocked.
From that point on we began to work. And it was a
very short period before we had sold the bonds. [7]
|
The parking lot on the grounds of the Gateway
Arch, May 1978. NPS photo.
|
By 1983, the National Park Service and Bi-State
Development Agency amended their formal agreement for the operation of
the Arch trams to expedite the financing and construction of the Gateway
Arch parking garage. The agreement with the city for the operation of a
1,208-car parking facility on the 4.7-acre site was not changed; the
land was federally owned and subject to NPS control. Under a
lease/construction/management/operating agreement, the city supervised
construction, with Bi-State Development Agency the project director.
Funding for construction was provided by Bi-State with the sale of
$8,400,000 of Gateway Arch Parking Garage Revenue Bonds, Series 1983.
[8] The bonds were to be repaid from garage
revenue; however, more than $1.2 million of Arch tram funds were to be
held in a separate account to assure the bonds. No taxpayer funds were
involved in this innovative approach to providing badly needed parking
for visitors to the Gateway Arch. [9]
The garage was planned as a three-story structure,
with two levels below ground and the top deck built on a contour with
the Arch grounds. Superintendent Schober told the press that the area
would be more attractive once the garage was built, "Because most of the
cars will be hidden from view." It was planned that the top deck of the
garage could be used for special events as well. Fred Weber, Inc. of
St. Louis came in as the low bidder, and was awarded the contract for
$6,262,000 to build the garage. [10]
In March 1983, an environmental impact statement was
approved by the State Department of Historic Preservation. The impact
study was required since both the Eads Bridge and the Gateway Arch were
on the National Register of Historic Places. Since the construction was
to be implemented in an area of potentially significant archeological
discoveries, the project was monitored. At first, neither the city, the
park, nor Bi-State thought such monitoring would be necessary, since the
entire project was to be constructed on disturbed earth and landfill
brought in during the construction of the Arch and creation of its
landscape design in the 1960s and 70s. When the Missouri state historic
preservation officer raised the issue, recalled Jennifer Nixon, [11] "Bi-State telephoned several local
institutions for bids on archeological monitoring. Southern Illinois
University called first." [12] On February
2, 1984, at a meeting between representatives of Bi-State, the National
Park Service, the City of St. Louis, and Southern Illinois
University-Edwardsville (SIUE), an agreement was made with William I.
Woods, staff archeologist at SIUE, to supervise on-site archeological
monitoring. Artifacts recovered were retained by the park, and the
circumstances of their discovery and location were recorded. [13] The selection of Woods caused some
bureaucratic controversy, despite his excellent credentials and the fact
that he had worked on "historic sites of comparable age to the
riverfront in St. Louis . . . [as well as] a variety of 19th century
sites." [14] The controversy involved the
use of an archeologist not retained by the National Park Service's
Midwest Archeological Center.
Monitoring began on February 3, 1984. The upper
portions of fill dirt brought in during the construction of the Arch had
already been excavated by that time, but it was felt that "the 6 feet of
rubble that had been removed probably reflected the 3 feet that
remained." [15] As Superintendent Schober
remembered:
We didn't find anything. . . . We dug down to quite
a big depth and ended up finding streets underneath it with stone walls.
That much earth had been brought in as fill around the Arch. Even when
we [excavated for] the irrigation system in 1980-81 we were uncovering
tombstones and all that were not from the cemetery out here but that had
been hauled in as fill and dumped. Many of the old warehouses that were
where the garage sits probably had two sub-basements in them, and when
they razed them they must have just pushed one floor into another and
just dropped them. We really did not find any kind of major artifact
whatsoever. In fact, probably if we had, you would have wondered if it
was dug from somewhere else and brought out here as fill. [16]
A professional archaeologist monitored the
excavation intermittently on-site between February 3, 1984 and January
4, 1985. "During that time, SIUE personnel defined, mapped, and
photographed three stratigraphic profiles and six cultural features or
portions of features. None of these features is considered to represent
an intact cultural resource dating before 1849." The archeological
report stated that "the site appears to have only occasional foundation
remnants that have no dates or related material. The only material has
been recovered from the rubble which consists of some burned debris and
building materials. . . . This fill probably dates from the time the
area was leveled for Arch construction. Materials associated with the
rubble consist of building debris (bricks, limestone, granite blocks,
and some wood and iron). In addition, the rubble contains glass and
china dating from the early 1900's. The fill presumably extends to
bedrock (434.0 ft - 420.0 ft) in this area." [17] Although the area was found to have been
untouched by the 1849 fire, the conclusion of the archaeologists was
that post-1849 urban renewal had completely destroyed any earlier
structures, and the foundations and artifacts recovered were of little
historical value. [18]
There were several problems with the construction.
First, all the fill put in during several phases of construction and
landscaping on the Arch project had to be removed, down to the limestone
bedrock in some places. "We found all sorts of garbage in the fill,
including large metal objects such as old boilers," recalled Jennifer
Nixon, who served as the project supervisor for Bi-State.
The design for the garage used piers rather than
pilings in the structure, which turned out to be a costly decision. A
piling is a huge steel I-beam driven into the ground, on which the
concrete could rest. Instead, Bi-State accepted concrete piers, which
were poured in place, into constructed molds called casings. The area
for the casings had to be drilled out of the fractured limestone
bedrock, not an easy task. Fractured limestone has dolomite in it. We
needed to use an industrial-strength diamond bit. As we drilled, we
were hitting lots of stuff in the fill and struggling to get through the
dolomite. Then the water had to be pumped out; we hit natural springs
in two places. The casings needed to have a footing, so they had to
flange outward at the bottom. What a job! When going into this type of
limestone, it would have been much better and faster to use pilings. The
construction was slowed to the extent that the project had to be
re-financed on April 1, 1986. [19]
As the parking garage neared completion, Bi-State
and the Park Service made arrangements for its operation. It was agreed
that Bi-State would operate the facility and that the NPS would provide
protection and maintenance on a reimbursable basis. [20] This was problematical with NPS
officials in Washington, who maintained that the park would, in effect,
be charging a fee for providing a service, which was not acceptable
according to NPS policies. [21] "This was
something entirely new," recalled Jerry Schober.
We felt like it's called the "Arch Garage."
Everybody who comes there really thinks it's part of this facility, the
Arch, and they think they're protected by rangers. So when I found out
what Bi-State was going to have to pay for bringing private guns in, to
get security from an outside group, I tried to say to Ms. [Jennifer]
Nixon, for roughly $99,000 we'll give you twenty-four hour protection
and we'll have a uniformed ranger on-site. [22] Well, what I found out from the Park
Service was that you can't accept money that way. They would have to
give that money to general receipts. So, the first thing I decided to
do, I asked if they would donate that money. This is unheard of
by a quasi-political group such as Bi-State. They are, by the way,
legislatively charged to operate in Illinois and Missouri
anything in transportation. And [Midwest Regional Director Charles H.
Odegaard] said "If it's donated, yeah, I guess you can go ahead and your
people can operate it." So, [Bi-State] said they'd donate it. . . . All
of a sudden the Washington Office got that information. . . . We had
already hired the rangers, we had them in operation. And [Washington]
came back and said "That [money] wasn't donated. That would [be] just
like you requesting that money to be funded. And because of it we are
not going to spend one nickel of it, we are going to return it to
Bi-State." Meanwhile I've already hired rangers and everything is hot
to trot. [23]
The situation remained unresolved even after the
official opening and dedication of the garage on May 8, 1986. In the
meantime, the park provided the services despite having no funding for
them. Schober continued:
So, I felt like it was time for me to go to my
congressman and my senator. When I was in California, I asked one of
the most powerful representatives in the House, a guy named Phil Burton
. . . why he wouldn't pass a bill that said all the funds that the Park
Service generates stay within the parks, whatever park generated them.
He said no, because Congress wants all the funds sent to them and they
would allocate the money where they felt park needs required it. . . .
So I asked that of Dick Gephardt when I came here. And he too smiled,
and said no, for the same reasons as Burton. So then I thought, let's
try no park had tried this one . . . what about [our park,
specifically: Jefferson National Expansion Memorial? Then I] . . . went
to my Republican senator, Jack Danforth, and talked to him also. [24]
With the assistance of Senator John C. Danforth and
Representative Richard Gephardt, the park was able to achieve passage of
Public Law 99-591 in 1986, which granted reimbursable authority to JEFF.
This meant that non-Federal funds generated within Jefferson National
Expansion Memorial would stay in the park, and be used at the discretion
of the superintendent. JEFF was the only park in the National Park
System with such a provision in its legislation. [25] Subsequently, an agreement was
negotiated with Bi-State Development Agency, whereby the costs of
providing resource and visitor protection and certain maintenance
activities for the Arch parking garage were paid out of funds generated
at the garage, at no cost to the Service. [26] Superintendent Schober continued:
I was a little chagrined because I couldn't get
anyone from the National Park Service to come and cut the ribbon at the
dedication. I interpreted this as [meaning] this was so different and
so unusual, they were not going to be a party to be around in case it
didn't work. [27]
Finally, P. Daniel Smith, deputy assistant secretary
of the interior, consented to speak for the Park Service at the opening
on May 8, 1986. In a unique ribbon cutting ceremony, Norbert Groppe,
president of the St. Louis Board of Public Service, and Carl Mathias,
chairman of the Bi-State Development Agency, held opposite ends of a
large ribbon which motorists were invited to break through with their
cars, thus entering the new garage. [28]
The postscript to the garage story was perhaps the most exciting facet
of the entire project. Jerry Schober explained:
. . . Now, some of the creative, we might call it,
management that took place, included the fact that people weren't ready
to buy these bonds if they did not feel they had some security, since
the structure was being built on government property. It's not like the
bondholders could take it over and could take the business somewhere
else. And so something had to sweeten the pot. And what I ended up
doing was, from this money that Bi-State had been putting in a fund for
the National Park Service, we said that we would secure the parking
facility with the operation of the [Arch] tram. And I pledged, if my
memory serves right, $1,274,000 to keep it at that level, in a sinking
fund.
This fund was there for nothing but an emergency. .
. . We've come very close but we've never been in the red. So,
somewhere down the line, when all the bonds have been paid off, whoever
is manager of this park is going to find it was like winning the Lotto.
There will be $1,274,000 sitting in a fund. It's been nothing but the
protection to the bond holder and a guarantee from the Park Service.
But what we have here [with this parking garage] is an 8.5 million
dollar gift from the outside, and no one feels like they have been a
loser.
So, this park, maybe for the first time, tried to
show that there are many ways that you can manage, and that you can
manage within the structure of the Federal Government. Just because
it's different doesn't mean it's illegal. And so, after a while, we did
so many different things here, when Director Bill Mott was in, I tried
to get him to designate this as a demonstration park for no other reason
than if you have some unique things you want to try out, and since we
are near enough to a city to get support, since we have some very strong
friends that can help sometimes in bringing things about, let's try it
here. If it works here we will know it will work somewhere else. [29]
|
The completed Gateway Arch Parking Garage, from
Washington Street on the north side of the Arch grounds, April 1987. NPS
photo.
|
jeff/adhi/chap1-2.htm
Last Updated: 15-Jan-2004
|